Ensure that investment of 180 billion!Jiangsu years five railway will fully open, the latest progress of disclosure
these projects are pushing ahead with the prophase work
s orbit transportation
north along the river high-speed, has won the National Development and Reform Commission formally approved;Wang group approval "of the new south along the Yangtze river in jiangsu taicang intercity railway region by Shanghai yu rong introduced high-speed synchronous implementation class I change design.On January 4, 2022 high-speed along the river into the south north along the inter-city railway synchronous implementation of the project started construction.
sense of sujiahang ningbo railway: jiangsu Duan Keyan reply lead requirements have been completed, at present, the internal circulation of feasibility study report is wang group, completed party meeting, review will be submitted to the board of directors;Yancheng to nantong nantong railway to zhangjiagang period of synchronous design obtains the approval, the implementation of engineering change to pass her on the feasibility study after approval, can be realized through a period of construction.
salt Thai tin Chang Yi railway: the provincial development and reform commission approved double salt tai tin Chang Yi jiangyin to the feasibility report of the following stations, construction conditions.
in new railway: national railway group to block is adjusted for weifang diesel nest railway and the railway.The weifang diesel nest, railway jiangsu Duan Keyan review report has passed the appraisal center of wang group, is the feasible propulsion situation closely track the transtition group.
NingXuan railway: feasibility study report is moving forward, station to nanjing lukou international airport Duan Keyan feasibility study report has been Yang zhenning horse railway during the review meeting to report back to the appraisal center of wang group, is to further deepen the research related technology solutions.
Yang zhenning railway ma: feasibility study report to complete the transtition group identification center feasibility review, are actively coordinate the transtition group appraisal center issue advisory opinions as soon as possible;Standard bahn network scheme has wang Shanghai bureau group to review, is to coordinate its country, iron group as soon as possible;Social stability risk assessment completed expert evaluation, planning and site selection and use pre-examination is accelerating to submit for approval.
suxichang inter-city railway: taicang pilot period of taicang stations have been approved feasibility study report, preliminary design, and on January 4, 2022 to start the construction, the full feasibility study report basically completed.
has railway river-crossing channels: the door has door rail river-crossing channels to complete the feasibility evaluation report and submit it to wang group, obtain the feasible advice by the rules of China railway hospital, has been navigable evaluation expert evaluation work, is now in the accelerating water drilling, a review of the work.
Zhang Jinggao Yangtze river bridge: Zhang Jinggao Yangtze river bridge work, preliminary design and approved for first;Anchorage cable tower, order of merit a number of construction drawing has been completed, is organizing internal audit;Construction started construction in the large, main body construction, supervision bidding work is started.
nanjing lukou international airport: three phase of the terminal area work worldwide experts, formed three recommendations;Completed entry flight dedicated terminal area project.
nantong airport: complete preliminary feasibility study work, report the main content of the framework is stable, basic principles and military use in airspace coordination and coordination key aspects such as basic to reach a consensus.
changzhou rush NiuGuoJi airport: to complete the project construction, photovoltaic power generation and the airport airfield pavement maintenance engineering completion of commissioning.
: xuzhou guanyin airport airfield security ability raise the engineering (contain child engineering WeiJie against the invasion of engineering) to complete the preliminary design approval, and the comprehensive construction.
these construction projects smoothly
south along the inter-city railway, bridge engineering drilling piles, pile caps, pier body, box girder precast and complete the design of box girder erection are 99.2%, 99.5%, 98.4%, 94.6%, 87%;93.7% of the subgrade engineering conditions to complete the design.
NingHuai inter-city railway: huaian section of the requisition completed 83%;NingHuai first period project completed about 95%;Nanjing section has issued "about the new nanjing liuhe to huaian inter-city railway west to north the feasibility study report of the opinions, the provincial railway group in promoting the course evaluation to handle the work, after waiting for air review approval, however, nanjing Duan Keyan to the provincial development and reform commission (NDRC), further the feasibility report of the coordination work approval.
Shanghai sutong phase ii: preliminary design approval has been made, is to urge the construction unit to accelerate land group work.
Shanghai Su Hu inter-city railway: "SanDian" and line moved to change the total 83.1%;Across the pile foundation engineering progress completed 94.41%, shafts of the total 65.56%.
often Thai river-crossing channels: main channel bridge, the complete steel open caisson will sink, back cover, to complete the main tower caps, tower and pillar under construction, is carrying out beams under construction;Of the navigable Kong Qiao caps, pier construction steel truss girder erection and two internodes;Special channel construction of complete and 90% in the construction of the bridge pier.
the longtan river channels: the north anchor complete filling and roof construction of foundation pit;The north tower completed the 30th day pillar construction;The south tower to complete section 22 pillar construction;The south anchorage of complete construction of open caisson sinking.
the jiangyin jingjiang Yangtze river tunnel: 47.5% complete Ming dig tunnel construction;Two sets of shield machine manufacturing and transport work, start debugging assembly at the scene.
to ensure that the investment of 180.9 billion
5 railway comprehensive construction
transportation hall in jiangsu province party secretary yong-hong wu, this year, jiangsu will clear around 30 year major projects, ensure to complete the infrastructure investment of 180.9 billion yuan, built the comprehensive transportation network more than 2100 kilometers.
at a faster pace forward commonly Thai railways, such as general Su Hu railway, such as water punters pre-project, comprehensive construction north along the river high-speed, salt Thai tin Chang Yi railway, suha ningbo railway, Shanghai sutong railway phase ii and NingWu revamping/expansion of railway engineering, accelerate Su Hu NingHuai inter-city railway, Shanghai railway project construction, such as basic body built along the river south inter-city railway engineering, strive to start construction the river-crossing channels, hefei to suqian railways has door, weifang to suqian railway, etc.
built in gaochun to xuancheng jiangsu section of the highway, liyang to jiangsu section of ningde, reflected light to yancheng expressway project and yan road river-crossing tunnel project (southern), starts to suqian high-speed Xu Wei to lianyungang cloud section, yizheng to lukou airport highway corporation the shanghai-shaanxi expressway to the Yangtze river north some the river-crossing channels, the sea is too (large) in the project, etc.
built in zhangjiagang port projects of approach channel in the east of sand areas, nantong port three clamp ShaNa waterway engineering, etc.;Construction projects of lianyungang port 400000 tons of ore terminal, tongzhou bay harbor dredging port on the sea port channel new jianghai river waterway regulation project, the sea port to tongzhou bay port dredging port channel build hub project, to start the first phase of intelligent lianyungang port container terminal.
completed operation of nanjing lukou airport T1 terminal south corridor project.Start young Thai airport phase ii expansion, changzhou airport terminal area, the bull run huaian ripple water airport cargo terminal international area reconstruction project.Accelerate the lukou airport 3 period, the preliminary works such as nantong airport, airport to suzhou planning and construction of civil transport matters, support suqian airport planning research, etc.